Thursday, January 14, 2010

Kitchen Renovation - Days 5 & 6

After a peacefully quiet weekend, things are moving along at a steady pace on the reno.

The steel beam went in first thing Monday morning.


Andrew's bedroom now has heat.


Drywall is up on the dining room ceiling.


Family room is insulated and the strapping is up for the ceiling drywall.


Plumbing is roughed in for the island sink.


Best of all, the soil stack is moved to the back wall and all the pipes have been tucked into the ceiling so that the ceiling in all three rooms will be the same height.